The truck is only half the purchase

For a delivery company, a transit agency or a municipal works department, fleet electrification starts with a seductive question: which truck should we buy? It is the wrong first question. The vehicle is only half the purchase. The other half is the depot: the chargers, the electrical service and the daily charging schedule that decide whether the fleet saves money or creates a new peak demand problem. Get the depot right, and an electric fleet becomes one of the most flexible loads a building owner can control.

Start with duty cycles, not brochures

Before ordering a single vehicle, map how each truck actually works: daily distance, dwell time at the depot, payload and winter range. A delivery van that returns at 5 p.m. and leaves at 7 a.m. has 14 hours to charge and can live on a modest charger. A truck that runs two shifts with a 45-minute turnaround needs fast charging and a very different electrical plan. The duty cycle sets the charger size, and the charger size sets the electricity bill. Fleets that skip this step buy chargers they never use, or discover too late that their service cannot support the ones they need.

The depot is an electrical project

A depot with ten 60 kW chargers can draw 600 kW if every truck plugs in at once, more than many commercial buildings use at peak. That is why the first call should go to the utility and an electrical engineer, not the truck dealer. A service upgrade can take months and cost more than the first vehicles, so start it early. And remember that commercial electricity bills charge twice: once for the energy used, once for peak demand. Unmanaged depot charging can push a site into a new demand peak that costs thousands every month, even if the total energy is modest.

Managed charging is where the money is saved

The fix is managed charging: software that staggers charging, caps total site power and prioritizes the trucks that leave first. The Open Charge Point Protocol (OCPP) lets chargers from different manufacturers speak the same language, so a fleet is not locked to one vendor. With charging orchestrated against departure times and electricity prices, the depot charges overnight when power is cheapest, never all at once. Platforms such as Tenergen OS apply the same logic used for building loads to the depot, treating chargers as flexible loads alongside heating, ventilation and air conditioning (HVAC) and refrigeration.

Incentives have shifted, so check before you budget

The funding picture changed in 2026. Transport Canada's Incentives for Medium- and Heavy-Duty Zero-Emission Vehicles (iMHZEV) Program, which offered up to $200,000 per vehicle, closed on March 31, 2026. Provincial programs now carry the weight. In British Columbia, the CleanBC Go Electric Rebates program reopened on August 10, 2026, with point-of-sale rebates up to $130,000 for a Class 8 zero-emission vehicle, and the CleanBC Go Electric Fleet Charging Program covers up to 50 percent of fleet charger costs. In Quebec, the Écocamionnage program offers up to $100,000 for eligible battery-electric trucks under its 2025-2028 rules. Amounts and intake windows change, so confirm the current status before signing a purchase order.

A depot is a grid asset in waiting

Once charging is managed, a depot becomes something utilities value: a large, predictable, shiftable load. Some utilities already pay fleets to pause charging during grid peaks, and vehicle-to-grid technology, which lets trucks return power to the building, is moving from pilots to early deployments. The depot that is planned today as a flexible load is the one that can earn grid revenue tomorrow.

Plan the charging first

Electrifying a fleet is not a vehicle purchase. It is a depot project, an electrical project and a scheduling project, in that order. Fleets that plan the charging first buy the right trucks, avoid the demand-charge trap and end up with an asset the grid will pay for. The trucks will follow.